<aside> 💡 The activity statuses have been created to provide planners with a clearer overview of the current state of the project's components. Additionally, these statuses are used to filter activities across various modules, allowing users to access them only when they have the appropriate status.

<aside> 🎯

In this section, you will learn how to set up and manually change the status of your project activities in the Project module.

</aside>

</aside>

List of content

The Basics

Every created activity has a status property that indicates its state. The activity's status impacts its availability in other application modules.

Activity status can be selected manually or can be updated automatically depending on the progress of the activities assignments.

Default statuses

Statues can be customized by the users, but by default, we will have the following ones:

If all the activities of your component have the same status, the status of that component will adjust to match the activities.

The reverse operation is possible, as changing the status of a component will also change the status of the activities contained in it.

Walkthrough