<aside> 💡 On this page you can find the information regarding the Resource table that belongs to the Activities Tab in the Project module. Here is described the process how to edit the Resource assignment.
</aside>
List of content
Most activities contain at least one assignment that outlines what is needed to complete it. We can find it/them in the [ 1 ] Resource tab of an activity.
Having an Assignment/Resources associated with an Activity is essential to have a Task on which an employee can book hours and follow the progress of a certain activity.
Assignments/Resources [ 1 ] indicate in the table the following data:
All this data can be modified from the planning window except for the Worked hours, as they are booked directly by the employee in the Hours and Progress module.
Budget, Progress, Worked, and ToGo hours values are related and interdependent:
This means that, when modifying the value of the Progress, we update the ToGo hours and the reverse happens when we update the ToGo value.

All the above data and more can be edited in Edit Assignment pop-up.
In the edit pop up we can find additional fields such as Description, Planned Start, Planned Finish, calculation data fields and Codes ones.


<aside> <img src="/icons/friends_orange.svg" alt="/icons/friends_orange.svg" width="40px" />
The features are accessible to roles that have permission for the Project module.
This feature can be accessed by Advanced users.
If you aren’t sure what user you are, contact your Administrator.
</aside>
<aside> <img src="/icons/warning_red.svg" alt="/icons/warning_red.svg" width="40px" />
Requirements
Troubleshooting
</aside>
Edit an Activity in your project
Activity tab - create a new Activity